Background

Four years ago three members of the Davis City Council (Lucas Frerichs, Rochelle Swanson, and Dan Wolk) voted to approve a Development Agreement between the City of Davis and the New Home Company (the Cannery site developer) that granted entitlements to the New Home Company to construct 547 residential units and a Commercial District on the 100 acre former cannery site. Then Mayor Joe Krovoza and Councilmember Brett Lee opposed the project

Part of that Development Agreement was the construction of a “grade separated ” bike and pedestrian access tunnel or bike bridge that would provide a safe crossing of Covell Boulevard. Then Mayor Joe Krovoza, and Councilman Brett Lee in part, opposed the project because they had advocated for two “grade separated” crossings.

After the City Council voted for the final agreement, the Davis Enterprise reported that the developer agreed to provide two million dollars for completion of a single grade separated crossing which was the estimated maximum cost at that time.

However, the council vote to approve the Development Agreement took place before completion of the Covell Corridor Traffic Study. Vehicle traffic from the new Cannery residents was to be mitigated through measures identified in the Covell Corridor Study which would identify upgrades to Covell Boulevard. These measures would improve traffic flows along Covell Boulevard. Unfortunately, the
prior passage of the Development Agreement precluded requiring Cannery to completely fund these traffic improvements.

Further, the route and type of the “grade separated ” crossing had yet to even be identified. Subsequently, the Davis Enterprise reported that the New Home Company was only obligated to pay up to 1.4 million dollars while the actual cost would be $7 million for an over-crossing, and $10 million for and under-crossing of Covell Boulevard!

To date, the long promised grade separated crossing of Covell Boulevard to reduce vehicle traffic that was part of the original Development Agreement has never been constructed.

In 2016 the Cannery Developers submitted another modified proposal to amend their original Development Agreement with the City to construct 24 additional units to the 547 units and a “Marketplace Center” that were originally approved in 2013. Now they are back again with yet another significantly larger proposal for the “Leeland Marketplace” portion of the site. The current proposal also includes an additional 90 residential units in three three-story buildings. The Staff Report recommending approval of this current project is available on the City’s website at http://documents.cityofdavis.org/Media/Default/Documents/PDF/CityCouncil/CouncilMeetings/Agendas/20180220/05-Cannery-Marketplace.pdf

The Cannery project has been controversial from the beginning for many reasons. Many citizens opposed the first phase of the project because they thought the City rushed through a Development Agreement in 2013 that heavily favored the developer. Those opponents claimed, among other things, that the City Staff and Council were far too malleable and willing to accept both vague promises of future traffic mitigations (e.g. the long-promised grade separated crossing) and the imposition of Mello-Roos taxation fees on new residents to the City’s financial detriment.

Subsequent piecemeal amendments to the original Development Agreement added more residential units to the Cannery and were dutifully approved by our Council with exceptionally lenient review from staff. Many complained this was an extremely poor way to entitle land use development and set a bad [precedent] for future large scale land use policy in Davis. Indeed, It was against this backdrop of broad citizen distrust of the City’s development entitlement process that the first Nishi project failed at the ballot box in 2016.

It seems that the great Cannery give-away continues with this current proposal. For instance, the current Leeland Cannery Partnership proposal exceeds the upper limit for both residential and commercial development proposed in the original Environmental Impact Report (EIR) that was prepared for the project and certified by the City Council in 2013. As a result, an addendum to the original EIR is now proposed as well as revision of the Neighborhood Design Guidelines, a Conditional Use Permit, and yet again amending the Development Agreement with the City of Davis. The Leeland Cannery proposal is now scheduled to go before the Davis City Council at 7:05 PM on Tuesday, February 20th.

Current Project Deficiencies

This current development scheme asks for much more than what was in the original Development Agreement yet offers precious little to the City in terms of financial compensation or mitigation for their impacts on the City. Consistent with their previous passive approach to hard negotiations with any developer, our City Planning Department appears functionally uninterested in even asking for modest additional concession commitments from the developer even though this development project has, on balance, gotten far more entitlements from the City than was originally granted in the original Development Agreement.

Unfortunately for the City, however, this project still has enormous deficiencies, as follows:

Still No Grade Separated Crossing Across Covell – Most notably, the long promised grade separated crossing of Covell Boulevard to facilitate bicycle and pedestrian access and reduce vehicle traffic impacts by the project that was part of the original Development Agreement has never been constructed due to delays in funding. As it currently stands, it appears the grade separated crossing will never be built unless the City makes a substantial monetary contribution or requires the Cannery to fulfill their original promises. These assurances are not addressed in the current development proposal.

Unmitigated Traffic Impacts Not Addressed in the Addendum to the EIR – The current proposal also will now generate far more traffic impacts that exceed those projected in the original EIR which used recession-level traffic counts to generate their original traffic baseline. These baseline counts are now far exceeded and the Leeland project itself will generate far more additional traffic than originally projected for this phase of the project. The addendum to the original Environmental Impact Report does not properly evaluate these new huge impacts based on current conditions and otherwise invites litigation because of these deficiencies and the adverse traffic impacts on the community.

For instance, the access to the Leeland Marketplace site is inadequate for a development of this scale. Market Avenue, its central access point, is not signalized and will only allow right hand turns into the marketplace from Covell and right hand turns to exit the Marketplace onto Covell. This will force 50% of the anticipated traffic to or from this development to “u-turn” at either the main Cannery entrance off of Covell to the east (if they are heading east on Covell and want to go to Marketplace) or at the F Street intersection to the west (if they are exiting the Marketplace and want to head east on Covell). This has not been properly evaluated in the addendum to the EIR the Council is considering for certification nor proposes acceptable mitigation.

Further, the anticipated multimodal transportation center that was touted and promised before the Davis City Council in 2013 when the original Development Agreement was approved now consists of a single bus stop.

Existing Single Bus Stop

Now, the envisioned multimodal transportation hub has been completely removed from the site plan in favor of more commercial development on the anticipated multi-modal transportation center site.

Instead of being centrally located and inviting and encouraging mass transit usage by residents and visitors, the single-bus stop currently in the plans is not even centrally located but instead faces the long blank back wall in back of one of the commercial buildings thus forcing bus users to walk around an entire building to get access to any of the project’s buildings. This was proposed by the developers for the sole purpose of building additional profitable buildings at the project to the disbenefit of non-automobile-using residents and visitors.

Proposed New Single Bus Stop

The new developer-sponsored traffic study now estimates nearly 10,000 daily motor vehicle trips to the Leeland Center. However, this estimate is based on the assumption that the grade separated bike crossing (that currently is inadequately funded) is in place when the Leeland Center is complete. There are no assurances that this will occur.

Further, the original baseline traffic analysis that was completed during the Great Recession is sorely out-of-date and does not adequately account for currently higher anticipated traffic both on Covell and to the development itself. The entire Cannery development, when fully built-out and occupied, will have Davis residents clamoring for additional traffic enhancements that will improve traffic flow on Covell.

In addition to signalizing the Market Dr. intersection into the Cannery and allowing two way traffic flow on Covell into and out of the project, it is likely that Covell Blvd. may need to be widened, impacting the adjacent Covell Blvd. overpass of the railroad tracks.

Additional modifications to F Street and/or Cannery Dr on Covell will also probably need to be prioritized to reduce congestion further increasing the City’s infrastructure deficit. These improvements are only needed because of the Cannery project. Yet the Cannery’s traffic impact fees are substantially inadequate to fund these necessary changes.

Access by bicycle will also be less than optimal due to the inadequate funding to complete the grade separated crossing and failure by the City Staff and Cannery project developers to identify and provide the easements which are necessary for construction to complete connection with the rest of the City neighborhoods. Students that could bike to Holmes Junior High and Davis High School from the Cannery will probably instead be transported by their parents by automobile, further increasing congestion at these school sites and neighborhood streets. Mass transit access will also be diminished by the poorly-placed single bus stop at the project.

Insufficient Affordable Housing – In December 2017 the Social Services Commission reviewed the Addendum to the Cannery Project’s Affordable Housing Plan with the proposal for only two additional affordable units to meet the Project’s affordable housing requirement. The Social Services Commission voted 6-1 to instead recommend that the applicant provide 9 affordable units, consisting of 5 low income units and 4 very low income units.

The Commission specifically noted that additional low income housing should be provided because of the extra considerations otherwise requested by the project in terms of density and exceptions to the original Development Agreement.

Entitlement of a newly-proposed “Big Box” Chain Fitness Center May Decimate Locally-Owned “Mom-and-Pop” Neighborhood Fitness Centers – The current proposal also entitles a new 34,000 sq. ft. Fitness Center rumored to be a new LA Fitness facility. This proposed Fitness Center will be far larger than any in town and exceeds the 25,000 sq. foot limitation for building size in the original Development Agreement.

Indeed, it will dwarf the locally-owned Get Fit Davis facility nearby on Picasso Drive. This functional equivalent of a “big box” store will be extremely predatory to the many small locally-owned “mom and pop” neighborhood fitness centers painstakingly built-up throughout the City. These facilities provide local convenient exercise opportunities to many residents and gainful employment to many more employees than will be provided by a minimally-staffed, large-scale, “big-box” fitness center.

Amazingly, however, the Staff report touts their recommended approval of this aspect of the project, as follows;

Staff finds that the Cannery Marketplace is an appropriate location for a large fitness center. The site is centrally located in City and is convenient to nearby residential neighborhoods. It provides adequate access and parking with convenient transit access and connections to the City’s bicycle network. To the extent that commercial recreation uses may gravitate to the City’s existing light industrial or business park areas because of space and building square footage needs, this site helps to ease that pressure on those job and business centers.”

Firstly, for all practical purposes this fitness center is on the very edge of town (as is the entire Cannery project) and is far from centrally located, as otherwise claimed by Staff. Secondly, as we have discussed above, this Fitness Center will hardly be a convenient place to access via automobile due to the horrific traffic bottleneck that will ensue during commute hour as a direct result of project-generated traffic increases that are otherwise unmitigated.

Access by bicycle will also be less than optimal due to the inadequate funding to complete the grade separated crossing and failure by the City Staff and Cannery project developers to identify and provide the easements which are necessary for construction to complete connection with the rest of the City neighborhoods. Mass transit access will also be diminished by the poorly-placed single bus stop at the project.

Additionally, it is completely speculative that this newly-proposed largest Fitness Center in Davis may open up other commercial space that is now or otherwise would in the future be needed by other Fitness Centers. Staff implies that this newly-proposed Fitness Center will allow other businesses to enter such space and generate jobs that might otherwise be available if a Fitness Center were put into any such commercial space.

Staff has also neglected to inform Council that all existing Fitness Centers in Davis can now accommodate more customers that they currently have which might otherwise be siphoned off (along with existing customers) by this newly-proposed mega-Fitness Center. Thus, this imaginary new commercial space would only open up only if these existing neighborhood Fitness Centers were shut down, thus eliminating their convenience to other Davis residents and eliminating existing paying jobs for dozens of employees and independent contractors.

Finally, Davis has a history of inviting and protecting stable locally-owned and home-grown businesses from predatory national chains. This practice must continue in this instance, especially since the City essentially gets nothing in return for this entitlement.

Sustainability Features

According to the Staff report, “The Cannery Marketplace structures would be designed to meet equivalent U.S Green Building Council LEED® Silver standards.” This is a real step backward in terms of sustainability standards for new commercial development in Davis.

Every major proposed and approved commercial or multi-family development project in the recent past (including the Marriott Extended Stay Hotel on Mace and 2nd Street in east Davis, the Hyatt Hotel on Cowell in South Davis, Sterling Apartments on 5th Street., Lincoln 40 apartments on Olive Drive., and the recently approved Nishi 2.0 project) have proposed meeting building standards equivalent to LEED Gold in addition to agreeing to purchase all excess energy not produced by onsite photovoltaics from the local Valley Community Choice Energy at the fully renewable rate.

It is difficult to imagine why Staff and Council would otherwise agree to any diminishment of these standards by this new commercial/residential development.

Conclusions

We want to be clear on one point – A marketplace center that is appropriate in design and scale with proper developer-funded traffic mitigation would be an asset for the Cannery and Davis.  However the subsequent amendments to the Development Agreement between the City and the Cannery Developers have gone in a negative direction for the City of Davis, particularly from a traffic management and financial standpoint in light of these very marked project deficiencies.

City Council should reject Staff’s recommended approval of this project and direct Staff to renegotiate a number of critical items before accepting future modifications to the Cannery’s Development Agreement and other entitlements. The priorities must be:

1) To protect existing neighborhood business from predatory big box commercial development (as is the City’s long-standing practice) by conducting an exhaustive analysis of community Fitness Center needs through engagement and cooperation with the many Fitness Centers throughout Davis.

2) To demand substantial traffic-mitigation monies for Covell Blvd. to reduce the city’s mounting infrastructure deficit and protect protect taxpayers from short and long term financial obligations that essentially subsidize the developers.

3) To provide significant funding to provide adequate grade separated connectivity of the 100-acre Cannery site with the adjoining streets and neighborhoods and to provide the necessary Right-of-Way easements for this crossing.

4) To provide for the multi-modal transportation hub promised by the original Development Agreement.

5) To increase affordable housing units to 9 units consistent with the recommendation of the Social Services Commission.

6) To demand LEED Gold (or equivalency) building standards and require all electrical energy not provided by onsite solar PV be purchased from the local CCE at the fully renewable rate.

Our City Council must recognize that substantial distrust by residents exists with respect to how developers manipulate our Staff and the entitlement process for new construction projects. And the Cannery, in particular, has become the poster child for past failures to extract sufficient concessions to cover even minimum mitigation costs necessary to reduce adverse impacts to the City posed by these large new development projects.

It is ill-advised that the Council would approve further developer give-aways in this particular project, which will otherwise cost the City millions of dollars to cure the resultant deficiencies while at the same time asking the residents of Davis to approve two parcel tax measures ($49 for Parks and $99 for Streets) in June to address our fiscal deficits. The optics of approving this project, as is and without any significant concessions from the developers, would not seem to be favorable to passage of these parcel tax measures in June.



Enter the maximum amount you want to pay each month
$
USD
Sign up for

About The Author

Disclaimer: the views expressed by guest writers are strictly those of the author and may not reflect the views of the Vanguard, its editor, or its editorial board.

Related posts

18 Comments

  1. Keith O

    Many complained this was an extremely poor way to entitle land use development and set a bad president for future large scale land use policy in Davis.

    LOL, Freudian slip?

  2. Ken A

    The new Cannery intersection and painted bike lanes make it work real well for bikes and the new bus stop looks fine.  I would be surprised if even a single person that lives (or plans to live) in the Cannery that likes riding their bike would chose to drive just because there is not a “grade separated” way to cross Covell or that someone who regularly takes the bus won’t take it to the Cannery because they have to “walk around an entire building”.  I have kids who ride bikes and I like the “grade separated” crossings and I like nice looking centrally located bus stops, but I also don’t know (or have even heard of) a single person that decides to drive vs. ride due to the lack of a “grade separated” crossing or drives vs. taking the bus because they have to “walk around an entire building”.

    P.S. Unless the people from the Cannery are going to visit friends in the apartments south of the place or going to go to a little league game they are going to have to cross a street “on grade” eventually (even if they get past Covell using the new $7 million overcrossing or $10 million undercrossing)…

     

  3. Dianne C Tobias

    Thanks to the authors for their  article which brought back frustrations over the handling of the Cannery agreement and developer promises etc while informing me on their new asks.

    Perhaps another issue is that we are trading a farm oriented market with a big box fitness center. I’m all for fitness and in fact support one of the locals in town but to me this is not a good trade except for the developer. Besides traffic increasing the Cannery residents will lose a walkable market and the ambience of the farm-oriented whole Cannery is lost.

    Remember the developer’s ads for the farm, the barn the produce??

    1. Ken A

      The Cannery already has a “walkable market” since it is just across Covell from the big Davis Nugget (the best grocery store in the entire Sacramento region).  As a bonus the Cannery is also across the street from Pink Donut (the best donut store in Davis)…

        1. Ken A

          It is just ~500 feet from the corner of the Cannery to Pink Donut and ~410 yards from the corner of the Cannery to Nugget.  It is almost 3/4 mile from the NW corner of the Cannery to the SE corner so any retail on the site will still be a decent walk for some people.  At the end of the day almost no one will ever walk to a grocery store with free parking in front and few people will walk when they can drive (or ride towing the Burley behind the bike) since when most people go “grocery shopping” they buy more than they can easily carry.

  4. Keith O

    The stop light at the Cannery entrance needs to be adjusted to create more flow on Covell.  Currently it gives J St way too much time.  After it turns green for J St a few cars will pass but it remains green for a long time after that while travellers on Covell just sit there.

      1. Keith O

        If as many people read the Vanguard that David claims I’m sure the some of the eyes that can make a change will see this.  Also others that experience the same wait at that light might also weigh in.  Either way part of this article is about the Cannery traffic so I thought I would give my opinion.

  5. David Greenwald

    Here’s a clarification.

    Alan wrote: “Still No Grade Separated Crossing Across Covell – Most notably, the long promised grade-separated crossing of Covell Boulevard to facilitate bicycle and pedestrian access and reduce vehicle traffic impacts by the project that was part of the original Development Agreement has never been constructed due to delays in funding. As it currently stands, it appears the grade-separated crossing will never be built unless the City makes a substantial monetary contribution or requires the Cannery to fulfill their original promises. These assurances are not addressed in the current development proposal.”

    If you look at Iem 8, page 12 on this week’s agenda:

    “CIP No. 8288 Cannery Grade Separated Crossing Project

    Mark Thomas professional services is working on wrapping up the 100 % design. There was a late edition to the scope for lighting along the undercrossing trail. Staff is hoping to bid the project in mid-January, open bids in February, award in Feb/March, construction start March/April. The last budget report indicated that there is about $4,674,458 of unencumbered funds. The last cost estimate showed construction cost of just over $2M. Costs may increase for lighting. Council also indicated that a HAWK signal is desired for the crosswalk at F Street between the Davis Little League field and Community Park. This will delay the project to add this component so the HAWK is being evaluated by Mark Thomas and may be added as a separate project following this project. There are sufficient funds based on the cost estimate, including a 10% contingency, staff time and the potential HAWK edition.”

    1. Todd Edelman

      The planned route from the Cannery to Community Park is as follows:

      Walk or bike to extreme southwest corner of area;
      Go under East Covell bridge;
      Go up as path bends to left, up to the east side of the E. Covell crossing;
      Go west on new path that leads down to the east side of F St. At this point there is a extremely tight hairpin turn towards E. Covell along the east side of F. (This turn is okay for ADA-compliance but annoying or worse for faster-moving cyclists. Mark Thomas has no idea how to design cycling infrastructure; their status as an in-house consultant needs to be re-evaluated);
      Activate crossing light and cross to Park (There will be a crossing guard here during school hours).

      This is an annoying crossing but as part of a connection between the Cannery and North Davis it is simply absurd. If the fence on either side of the train tracks stays intact, from the connection described above to stay on a non-motorized path it will be necessary to either cross W. Covell in Community Park or go back around past the baseball field.

      While some kids will have to take this route, it seems less likely for anyone who has a car and is visiting either the fitness center or really anyone at the Cannery. You can practically shout to someone on F St. from the Cannery. The people selling homes there have no idea that the Julie Parstansky Pond exists. The city park in the Cannery has much less value too when it can only be easily-accessed from the neighborhood that it would help most by crossing a busy and fast street.

      In all honesty the best use of the millions used for this offal would be better spent paying people to keep on cutting the fence and then carrying people as necessary over the tracks, under the E. Covell bridge.

  6. David Greenwald

    “Further, the anticipated multimodal transportation center that was touted and promised before the Davis City Council in 2013 when the original Development Agreement was approved now consists of a single bus stop.”

    This was the plan when when the original Development Agreement was approved – there was a single bus stop.  It was shifted to Covell, it hasn’t changed in the last four years and the facility itself hasn’t changed since the original approval.

  7. Tia Will

    I see this article as highly relevant to the today’s first article on the positions taken by Ezra in his campaign for City Council. Although some may read his comments as relevant only to the current council, I see a much broader view relevant to many city councils decisions which have tended to favor developers, sometimes with the deviations from initial promises as seen with the Cannery.

    Whether one likes, or does not like, or simply does not care about the existence of a grade separated crossing, this is a clear case of the developer not meeting agreements, but still asking for more allowances from the city.

  8. David Greenwald

    There is also one more correction related to the image in the post with claim that the building blocks access to the transit stop. The image in the post is an old one from the PC packet instead of the revised one from the CC packet.  The transit access is not blocked by a building: see page 6 of the CC staff report for the breezeway that was integrated at staffs request since the Planning Commission hearing.

  9. David Greenwald

    UPDATE

    From the city: “At the request of the applicant, tonight’s hearing on the proposed Cannery Marketplace revisions is postponed. The hearing will be re-noticed when it is rescheduled.”

    1. David Greenwald

      My only disagreement is the term bait and switch in the title. It’s really as I told someone else a “here we go again” moment of going back to the drawing board to revise something that they didn’t do right or failed to anticipate. It’s not even really a big deal, it’s just, here we go again, five years later, still having to revise this project.

Leave a Reply